51IceCube Project Monthly Report – May 2009 Accomplishments • The IceCube 59 string run (IC59) began on May 20, 2009. The new run includes many improvements to the data acquisition software. The transition from IC40 to

IceCube Project Monthly Report – May 2009 Accomplishments • The IceCube 59 string run (IC59) began on May 20, 2009. The new run includes many improvements to the data acquisition software. The transition from IC40 to

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
52IceCube Project Monthly Report February 2010 Accomplishments •  The Seasonal Equipment Site (SES) was winterized and flagged in preparation for

IceCube Project Monthly Report February 2010 Accomplishments • The Seasonal Equipment Site (SES) was winterized and flagged in preparation for

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
53IceCube Project Monthly Report – March 2009 Accomplishments • Completed the first meeting of the IceCube Software & Computing Advisory Panel at UW on March 24-25.

IceCube Project Monthly Report – March 2009 Accomplishments • Completed the first meeting of the IceCube Software & Computing Advisory Panel at UW on March 24-25.

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
54Popcorn Neutrinos Background At a glance

Popcorn Neutrinos Background At a glance

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
55IceCube Project Monthly Report - September 2010 Accomplishments    •

IceCube Project Monthly Report - September 2010 Accomplishments   •

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
56IceCube Project Monthly Report - September 2009 Accomplishments • The Integrated Master Schedule and Master Site Plans for drilling and cabling this season are complete.

IceCube Project Monthly Report - September 2009 Accomplishments • The Integrated Master Schedule and Master Site Plans for drilling and cabling this season are complete.

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
57IceCube Project Monthly Report - July 2010 Accomplishments • Simulation production of 59-string neutrino events continues to exceed predictions, with worldwide collaborators contributing to processing.

IceCube Project Monthly Report - July 2010 Accomplishments • Simulation production of 59-string neutrino events continues to exceed predictions, with worldwide collaborators contributing to processing.

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
58IceCube Project Monthly Report – February 2009 Accomplishments • On-ice drilling and installation activities were completed at the South Pole with the installation of 19 strings over the course of thefield

IceCube Project Monthly Report – February 2009 Accomplishments • On-ice drilling and installation activities were completed at the South Pole with the installation of 19 strings over the course of thefield

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
59IceCube Project Monthly Report January 2010 Accomplishments •  Drilling and string installation ended ten days early this season with twenty

IceCube Project Monthly Report January 2010 Accomplishments • Drilling and string installation ended ten days early this season with twenty

Add to Reading List

Source URL: icecube.wisc.edu

Language: English
60Microsoft Word - October 2007-Rev1.doc

Microsoft Word - October 2007-Rev1.doc

Add to Reading List

Source URL: icecube.wisc.edu

Language: English